Open meeting 1 PM, Irish Beach Firehouse, 15401 Forest View.

 

CALL TO ORDER:

 

The meeting was called to order at 1:00pm at Irish Beach Firehouse, 15401 Forest View.

 

IBADC Board members present: Chairman Chuck Conner, Directors Jim Day, Nik Epanchin and Gordon Moores.   Director Jim Albert was absent.

 

Others in attendance:  Bettye Winters, Bill Mackie, William Moores, James Counts, Ruth Cady, Roger Bean, Judy Murray, Kathy Edelbrock, Al Thompson, Debbie and Jerry Trujillo, Walt and Susan Rush, Don Jassowski, Tim Murray, Alex and Cathy Corey and Rick Morton.

 

APPROVE MINUTES:

 

Approve minutes of November 20th, 2004:  Nik Epanchin submitted the following amendment to the November minutes to be inserted into the discussion of William Moores 7/15 Phase I application (on page 2, just ahead of the sentence dealing with the incomplete mailing that starts with “It was noted that due to an oversight, 2 neighbors …..”):

Stock/Hemingway (7/12) submitted a written concern that they will not have room for a detached garage, the committee noted that there are 66 feet between 7/12 and 7/15.  The County will require the 7/12 garage to be set back 20 feet from their east property line, leaving 44 feet for a garage.  The Moglias (7/13) submitted written concerns regarding the proposed septic system, the inadequacy of the drainage plan and of the view corridor analysis and the requested back yard variance.  The Trathens (7/26) submitted a written statement expressing their general disappointment with the quality of the submitted package.  The committee addressed all these issues.”

 

Jim Day moved to approve the November 2004 minutes as amended.  Gordon Moores seconded and it was passed unanimously.

 

NEW BUSINESS:

 

COMMITTEE DISCUSSION:   The Committee addressed several issues that have arisen in recent meetings for the purpose public discussion and clarification of ADC policies.

Building Separation and Setbacks:  The minimum distance required between buildings is 28ft in Units 1 & 2, 32ft all other units and is measured eave to eave.  Ideally, neighbors with 14ft and 16 ft set backs on each property share the burden of the separation equally.  If the proposed separation is less than the required minimum or if an owner wishes to build less than 14ft or 16ft from the lot line there must be agreement between neighbors as well a variance approval.  ADC will require any such an agreement to be publicly recorded and attached to the grant deed in order to ensure the agreement shows up in a title search.  ADC will also require a notarized copy for its records.  The process of recording such a statement on the deed is simple and inexpensive.  James Counts stated that both his neighbors have less than a 16’ setback, which affects his buildable area if the 32ft separation is required.  Chuck explained that that type of situation could be addressed by a variance.  Al Thompson gave his opinion that set backs should be measured from the foundation, not eave to eave.  William Moores agreed and argued that measuring from eaves further reduces the potential building envelope on already problematic lots.  Gordon stated that more separation is desirable and that eaves have an impact on views.  Jim Day noted that CC&R 5.3 does not state foundation, but rather ‘dwelling’ and ‘structure’ and that ADC considers eaves to be part of a dwelling or structure.  In response to a question from Alex Corey, Nik recommended that, when applying for a Phase II variance, a prudent owner should consider submitting conceptual drawings rather than spending considerable monies on quasi final design drawings that might not be approved

Height Variances and Building Separation:  Chuck explained that the amount of a height variance must be added to the separation of buildings.  For example, a 4ft height variance would require an additional 4ft of building separation.  The burden of the additional separation is borne by the applicant.

Architect and Professional Architectural Designer:  This discussion addresses section 4.3(c) of the CC&Rs which states that new homes and major improvements must be designed by “a licensed architect or professional architectural designer”.  ADC interprets “professional architectural designer” to be any professional connected with architecture and building design.  ADC has responsibility for architectural aesthetic control in Irish Beach while the County has responsibility for enforcing construction and building codes.  Tim Murray pointed out that the Phase I portion of the Irish Beach Building Procedures for New Home Construction does not clearly state that an architect or architectural designer must prepare the site plan topography.  Chuck noted that the document should be clarified to conform to the CC&Rs.  Bill Moores suggested that ADC consult an attorney to get an opinion of the legal interpretation of the phrase “professional architectural designer” based on the California Business and Professions Code.   Bill speculated this is a legal matter and ADC may not have the authority to create its own definition of the term and should seek a legal opinion.  Al Thompson stated that he had been involved in putting the now disputed phrase in the CC&Rs and the intention of doing so was to include architects who are not part of AIA but are designing houses in this area.  After much debate, the Committee agreed to define a designer as someone who derives his or her income primarily from designing homes.  The issue was discussed further later in the meeting; see “Communications: Paoli” below.

Mean Natural Grade:  All applications must show the mean natural grade and elevations on the site and plot plans and on applicable elevation drawings.

Conditional Approvals of Applications:  Applicants whose plans will require a variance from the County of Mendocino will be required to show that the County variance process has been initiated before the Committee begins the review process.  The intention is to establish that a County variance is possible before the Committee and involved neighbors spends time, effort and expense on a review and hearing.

James Counts asked if the Committee is looking at drainage issues.  He stated that development of higher elevation lots effects drainage onto lower elevation lots.  Chuck explained that ADC procedures require a drainage statement in both Phase I and II applications.  The statement must describe how water from the lot will be handled, making sure it does not flow unto neighboring lots but ADC does not address overall drainage in Irish Beach.

ADC Meeting Schedule:  Beginning in February, meetings will begin at 11:00AM.  Beginning in March, meetings will be every odd month.  ADC, in it’s discretion, may schedule additional public meetings as needed.

 

TREASURER’S REPORT:  10/1/04-12/31/04:  The report was presented by Jean Selk.  ADC had a balance of $6826.41 on Oct. 1, 2004 and an ending balance of $6109.16 on Dec. 31, 2004.  Nik moved to approve the report.  Jim Day seconded and the motion was passed unanimously.

 

MACKIE 1/027 (14880 Navarro Way):  Application for Minor Exterior Improvement.   Mr. Mackie is applying for a propane tank enclosure.  Bill Moores stated that placing the enclosure west of the current trash enclosure is better for view preservation.  After reviewing the plans, the Committee noted that Mr. Moores’ suggestion would place the enclosure less than 10ft from the existing house and therefore is not an acceptable location.  Jon and Diane Heinzer had submitted a written statement approving of the location of the tank.  Nik moved to approve the application.  Jim Day seconded and the motion passed unanimously.  The Mackie’s permit number is 0105-0127 with an expiration date of April 5th, 2005.   Bill Moores also stated that Mr. Mackie’s trees have grown laterally to the point they are affecting views.  Mr. Mackie stated that in his five years of ownership he has removed some trees, topped others and is respectful of view corridors.  He agrees that his trees need to be trimmed laterally and he will attend to it in the near future.

 

MURRAY 2/64 (15061 Mallo Pass Dr.):  Application for Major Exterior Improvement.  Ms. Murray is seeking to build a garage addition which will require the altering the course of a waterway on her property.  Ms. Murray stated that she would like to alter the course of the waterway regardless of approval of the garage addition.  She contacted the County of Mendocino and was informed they do not have jurisdiction over waterways.  Chuck said she needs to contact Fish & Game and a warden will determine if they have jurisdiction and how to proceed.  Ms. Murray agreed to do so.  Gordon stated that redirection of the waterway may effect where her southern neighbor (Rose 2/65) can place his septic system.  Nik stated that a leach field must be 50ft from a creek if the field is of higher elevation.  Nik explained that it appears from the site map that the height of the proposed addition is 2.5ft to 4.0ft over the 16ft height limit for dwellings in unit 2 and the overage must then be added to the 14ft set back.  Three written comments have been received from residents regarding the project.  Norm Kucala (2/47) stated he has no objections to the application.  Jeffrey Rose (2/65) expressed concerns over the set backs and the effect of the waterway alteration on his lot.  William Moores expressed concern about the effect on views from unit 5 lot 2.  Ms. Murray agreeds that the view from unit 5 and from her neighbor’s lot will be affected.  Nik asked if she could build the garage with one story instead of two to ameliorate the view and height issues.  Ms. Murray stated that she is withdrawing her current proposal and will talk to her neighbors and Fish & Game.

 

VACANCY ON ADC BOARD:  Alex Corey, RJ Dial, William Mackie, Joel Kauffman and Walt Rush have informed ADC of their interest in serving on the Committee.  Mr. Dial has withdrawn his name from consideration.  ADC will ask the candidates to meet individually with the Committee on February 20th or make other arrangements.  The Committee will then inform the Irish Beach Improvement Club Board of Directors of its choice.

 

COMMUNICATIONS:

 

PASQUALETTI 4/17 (15575 Forest View Road):   11/30/04 Email advisement of various maintenance projects planned for the winter and spring.  Mr. Pasqualetti has been sent a letter of acknowledgement along with a request for a color sample if re-staining will result in a significant color change.

 

BRIDGER 3/63 (43701 Sea Cypress Drive): 12/3/04   Receipt of final plans and request for New Home Construction permit.  The Committee reviewed the plans after the meeting and found them to be in agreement with the approved Phase II application.  Only one set of plans was received.  A second set will be requested, signed and returned along with the final construction permit.  The permit number is 0404-0363 and expires on 4/16/05.

 

LEVENSON-PALMER: 1/032 (14840 Navarro Way):  12/3/04   Email notification of intention to replace their garage door.  The Levenson-Palmers have been sent a letter of acknowledgement.

 

COREY 3/10:  (14640 Cypress Point Road):  12/8/04   Receipt of Phase II application for New Home Construction.  A variance request was received on 12/14/04.  After review, the Committee rejected the Corey’s application and sent a detailed letter of explanation.  Mr. Corey stated that he understood the letter and was withdrawing his current Phase II application.  The Coreys are redesigning their house, it will be smaller than the one first proposed.

 

HARLEY 4/63 (15550 Forest View Drive):  12/7/04   Receipt of Phase I application for New Home Construction.  After review, the Committee rejected the Harley’s application and sent a detailed letter of explanation with a request for further documents.  The Harleys provided the documents on 1/14/05.  The Committee will review the documents and, if accepted, schedule a hearing for February 19th.

 

PAOLI ENGINEERING & SURVEY:  12/11/04  Letter to ADC describing the drainage system he engineered for the Moglia property (7/13) and stating that he had not designed the drain on the east side of lot 13 and therefore cannot speak to its extent or characteristics.  See minutes of Nov. 20th, 2004:  New Business- Wm. Moore’s application for New Home Construction 7/15.  Mr. Paoli’s letter will be taken into consideration when reviewing Mr. Moores application in the future.

 

PAOLI ENGINEERING & SURVEY:  12/11/04   Mr. David Paoli has informed ADC of his intention to begin designing homes in Irish Beach and requests notification as to whether he is considered qualified to do so under CC&R section 4.3(c).  Mr. Paoli is a registered professional civil engineer.  Jim Day stated that, in his opinion, Mr. Paoli is not qualified to design homes in Irish Beach (IB) because he does not earn his living as a designer and therefore does not fall within the ADC definition of “professional architectural designer”. Roger Bean, an architect, stated that the State of California Business and Professions Code allows the term ‘architect’ to be interchangeable with ‘civil engineer’ and therefore ADC may not have the legal authority to prevent Mr. Paoli from designing homes in IB. He explained that under California law a civil engineer is one of the groups of professionals who can legally design homes.  He also stated that regardless of who designs a home, ADC is able to reject the plans on aesthetic grounds, as it deems necessary. Nik agreed.  Gordon stated that he is not considering the legal or technical merits of who can design, but rather the intent of the CC&Rs.  He argued that one of the purposes of requiring an architect or professional designer is to increase the odds that an aesthetically sound design will be submitted.  In his opinion, Mr. Paoli does not meet the requirements of CC&R section 4.3(c) because he does not earn his living as a designer even though he can legally design homes under state law.  Nik argued that Mr. Paoli is a representative of Lindal Cedar Homes, which are designed by architects, and is certified within their system.  The Committee always has the authority to accept or reject a design on aesthetic grounds based on section 4.1 of the CC&Rs.  Chuck stated that Mr. Paoli’s letter suggests that he plans to begin designing homes and that the Committee may have to get the opinion of a lawyer.  He stated that it may be in the best interest of all IB property owners to require a licensed architect or professional designer because the aesthetic integrity of the community is paramount.  He expressed concern that without aesthetically competent applications, ADC may miss something undesirable in the plans, which will only become apparent when the home is built.  Nik moved to accept Dave Paoli for house design in IB.  The motion was not seconded.  Gordon moved that only people who earn most of their income from architectural design or a licensed architect be allowed to present applications and all others must have plans reviewed and signed by an architect.  After some discussion Gordon then moved to adopt as a policy that  ‘professional architectural designer’ as described in section 4.3(c) of the CC&Rs be defined as a person who has 3 years experience in designing homes and who has earned at least 50% of their income from design during that period.  Jim Day seconded.  Nik expressed disagreement with the 50% and 3-year stipulation and suggested the designer instead present a portfolio.  Gordon withdrew his second motion and moved that if a professional building designer is not a licensed architect he must submit a portfolio and get permission from the Committee that they think he is capable of making aesthetic judgments for the preparation of documents.  After more discussion, Gordon withdrew his motions and the Committee agreed to seek legal advice.  The Committee will to respond to Mr. Paoli’s letter by informing him that, until a lawyer is consulted, ADC is not prepared to answer his question and suggests that in view of the CC&Rs, he partner with an architect.  This will allow him to move through his current project (Harley 4/63-see above) in a timely fashion.

 

DROLET 1/107 (15225 Irish Beach Drive):  12/15/04 Receipt of documentation of third party construction delay.   Mr. Drolet’s permit will be extended by 7 months and 13 days due to third party delays.  The permit now expires on 4/4/05.  Nik pointed out that the third party delay documentation included a submission to the County indicating a structure height of 19ft above mean natural grade while the approved application was for a height of 16ft as stated in the minutes of 8/23/03.  Mr. Drolet will be requested to clarify the issue.

 

MOGLIA 7/13 (44515 O’Rorey’s Place):  12/15/04 and 1/6/04   Receipt of letters regarding Bill Moore’s New Home Construction project on 7/15.  (See minutes of 11/20/04).   The issues of eave to eave measurement and drainage have been addressed.  The Moglias expressed their refusal to allow Wm Moores to use their east curtain drain for disposal of surface run-off from his 7/15 project.

 

WILLIAM MOORES:   12/17/04   Letter listing concerns regarding the project of Judy Murray. (See ‘New Business’ above.)  Mr. Moores’ concerns will be taken into consideration when Ms. Murray resubmits her application.

 

TRUJILLO 3/1&2 (14470 Cypress Point Road): 12/20/04   Receipt of final construction drawings and documentation of third party delay.  The Trujillo’s permit will be extended by 5 months and 8 days due to third party delays.  The permit now expires on 9/25/05.  The Trujillios stated that the extension should be about 7 months, the ADC will again review the submitted documents and advise the Trujillios of its decision.

 

KUCALA 2/47 (14950 Mallo Pass Drive):  12/27/04   Email stating he has reviewed Judy Murray’s project (see ‘New Business’ above) and has no reservations.  The comment was noted in the discussion of Ms. Murray’s project.

 

HEINZER 1/067 (14861 Navarro Way):  12/28/04    Email stating they have reviewed Mr. Mackie’s project (see ‘New Business’ above) and approve of the location of the propane tank.  The comment was noted in the discussion of Mr. Mackie’s project.

 

HEMMENWAY-LADEROUTE 4/3 (15301 Forest View Road):  12/11/04 Receipt of Phase II application for New Home Construction.  ADC has requested additional documents from Hemmenway-Laderoute and expects to receive them in time to schedule a hearing on February 19th.

 

WM. MOORES 5/5 (43551 Sea Cypress Drive):  1/3/04   ADC letter to Mr. Moores listing additional documents and corrections needed before a Phase II application hearing can be scheduled.  ADC continues to work with Mr. Moores to make the application ready for a hearing.

 

WM. MOORES 2/41   (43925 Mallo Pass Court):  1/7/04   ADC letter to Mr. Moores listing additional documents needed to complete the Phase I application for New Home Construction.  ADC continues to work with Mr. Moores to make the application ready for a hearing.

 

ROSE 2/64 (15061 Mallo Pass Dr.):  1/12/05   Receipt of comments regarding the Judy Murray project. (See ‘New Business above).  The comments were addressed in the discussion of Ms. Murray’s project.

 

WM. MOORES 1/095 (44001 Noyo Way):  1/14/05 Advisement of intent to replace office door, canopy, and widen walkway.  The Committee has not yet reviewed the notification.

 

MOREALI 2/12 (44801 Arena Circle):  1/14/05   Request to have option to use Hardie Board siding with no color change.  ADC requests that the Moreali’s submit a sample.

 

TIM MURRAY 4/10 (15441 Forest View Road); 1/14/05 Receipt of Phase I application for New Home Construction.  The Committee will review the application and, if accepted, schedule a hearing date.

 

UNFINISHED BUSINESS:

 

BUCKE 4/18 (15601 Forest View Drive):  Issue of whether or not an after the fact permit extension is required.    Nik noted that Ms. Bucke did provide a document in October from her contractor indicating the start and end dates of construction.  Ms. Bucke has stated in writing that she does not intend to pay an extension fee.  The Committee will further investigate and determine the status of Ms. Bucke’s permit.

 

FROMWILLER 4/68 (15700 Forest View Road):  12/20/04   Notification from Ms. Fromwiller that the installation of her propane tank, woodshed and fencing was completed on 10/9/04 and request for closure of her permit.  It was explained that Ms. Fromwiller has requested a waiver of the extension fee due to her misunderstanding of the requirement that all outside work must also be completed within the permit period (except landscaping).

 

The issue of how to deal with unpaid extension fees was discussed.  The Committee will invite Ms. Bucke (if necessary) and Ms. Fromwiller to the February meeting to present and defend their case for non-payment.

 

HUNOLT 7/11 (44500 O’Rorey’s Place):   No reply has been received to ADC letter of 9/18/04 regarding excavation on property.  The Committee will retain an attorney to draft a letter to the Hunolts requesting their presence at the February meeting to discuss the excavation done on their property without a permit.

 

Chuck moved to adjourn the meeting at 3:50PM.  Jim Day seconded the motion and it passed unanimously. 

 

Next IBADC meeting:  Saturday, February 19th, 2005 at 11:00AM at the Irish Beach Firehouse located at 15401 Forest View.

 

 

Minutes submitted by Jean Selk