MINUTES for July 19, 2008

 

Open meeting beginning at 10:00am at the Rex Dunning Firehouse, 15401 Forest View Drive.

 

CALL TO ORDER

Acting Chairperson Nik Epanchin called the meeting to order at approximately 10:07AM.  He introduced Committee members John McGehee and Walt Salmen.  A quorum was present.  Leon Drolet and Gordon Moores were absent. 

 

Others present:  Roger Bean, Debra Lennox, Diane Taylor, Karl Taylor, Al Thompson, Loretta Thompson, Steve Whitaker, Su Whitaker and Bettye Winters.

 

APPROVE MINUTES/TREASURER’S REPORT:

Approve minutes of 5/17/08:  Nik moved to approve the minutes.  John seconded and the motion passed 2-0 with Walt abstaining.

Treasurer’s Report:  4/1/08-6/30/08:  John moved to approve the report as submitted.  Nik seconded and the motion passed unanimously

 

NEW BUSINESS:

 

Hearings for New Home Construction and Major Exterior Modification permits will be limited to 45 minutes; 15 minutes for presentation and Committee questions and 30 minutes for audience input and discussion. 

 

 

RAPELJE 1/003 (15400 S. Hwy 1):  Revised New Home Construction Phase II application with a height variance request.  One comment was received from William Moores (2/03).  Architect Debra Lennox presented the application.  She explained that this is a revision of a previously approved house, which had a height variance of 3’6”.  They are now requesting a height variance of 2’0”.  The size of the house has been downsized from approximately 3000ft2 to 1200ft2  due to requirements related to the septic system and financial consideration.  The septic system design required moving the location of the house and changing the foundation from slab on grade to a crawl space design, which raised the floor level.  The house is still located within the approved building envelope.  The proposed house has a 5:12 roof pitch, which is preferred when using interior trusses.  She also explained that they plan to build the house in three phases, with the current proposal being the first phase.  A garage and an expansion of the house will comprise the next phases.  County approval is conditioned on the results of the final Point Arena Mountain Beaver study and approval of the septic system.  Nik stated that variances are granted based on hardship and that a variance request letter is essential to explain the hardships.  He suggested that the garage be included in this proposal in order to raise the mean natural grade and thereby lessen the height variance.  The garage does not have to be built at this time, but approval now will eliminate the need for an application hearing in the future.  The current design includes screened parking.  Ms. Lennox agreed to the proposal.  Nik moved to approve the application pending receipt of a detailed backup letter enumerating and explaining all the hardships involved.  At a minimum, this letter is to address a)the septic system changes which are forcing them to raise the floor from elevation x to y, b)explain why 5:12 roof pitch is deemed appropriate at this time in order to accommodate the future expansion, c)incorporate the garage into this Phase II if it will raise the mean natural grade, and d)indicate by dotted line on a site plan the possible future expansion(s).  Walt seconded and the motion passed 3-0.  The variance letter will be mailed to neighbors and a 30-day comment period will be observed.  If no objections are raised, Rapelje will already have approval for the garage and will only have to pay the fee for a Major Exterior Modification permit. 

 

MOGLIA 7/13 (44515 O’Rorey’s Roost):  Minor Exterior Improvement permit application for a deck.  No negative comments were received.  Walt moved to approve the application.  John seconded and the motion passed 3-0.

 

 

 

 

 

COMMUNICATIONS:

 

TILLER 1/014 (15150 Irish Beach Dr.):  7/10/08  Receipt of final construction drawings for Major Exterior Modification permit 0707-1014.  The plans were reviewed and approved. 

 

McCormick 1/029 (14870 Navarro Way):  6/2/08  ADC letter explaining that the flat roof variance is on hold until connecting tape is installed on the story poles.  The McCormicks informed the Committee that the County may require changes to the house and will wait for their decision before reinstalling the story poles and continuing the variance process

 

SUMNER 1/047 (Navarro Way):  6/21/08 The Sumners submitted a Phase I application for a New Home Construction permit but withdrew it due to septic permit issues.  

 

CONNER 1/063 (44000 Noyo Way):  6/10/08 Receipt of location verification for Major Exterior Modification permit 1005-1063.

 

SCHEAFFER 2/21 (44641 Pomo Lake Dr.):  5/20/08  Receipt of final construction drawings for New Home Construction permit 0307-0221.  The Committee did not approve the drawings and replied to the Scheaffers in writing on 5/30/08.  The Scheaffers submitted an incomplete set of revised drawings on 6/13/08 with a request to waive the requirement that drawings be done by a licensed architect or approved professional architectural designer.  The Scheaffers now have a new architect, Lyndon Ernst, who will submit new drawings.  The ADC rejected the proposal to add an outside stairway to access the upper deck because it would encroach into the 14ft east setback.  In addition to providing a corrected site plan and the four new elevation views, Lyndon Ernst, who has visited the site will attached an architect’s statement and a detail of the new interior access to the deck over the garage.

 

HUMPHIES/HYMANS 2/45 (15000 Mallo Pass Dr.):  7/10/08  Notification of plans to replace some of the windows and siding and to re-stain the house with no color change. 

 

POTT 2/66 (15125 Mallo Pass Rd.):  6/2/08 Notification of their plans to paint the house and replace the deck with no change in size or dimensions.  Color samples were submitted and approved.

 

WOLFE  3/39 (43600 Sea Cypress Dr.):  5/22/08  Receipt of final construction drawings for Major Exterior Modification permit 0308-0339.  The plans are approved.

 

LIMBERG/WHITNEY 4/72 (15780 Forest View Court):  6/3/08 Receipt of final construction drawings for New Home Construction permit 0108-0472.  The plans are approved.  7/2/08  Notification that construction will begin on 7/7/08.

 

MOORE 7/09 (44520 O’Rorey’s Place):  7/17/08  Dan and Marsha Moore have requested the addition of eaves beyond what was approved for the garage, which is currently under construction.  The Committee members made a field trip at the end of the meeting to review the request and concluded that the addition of eaves would be an aesthetic improvement and will probably have minimal impact on views.  The ADC will ask Mr. Moore to place 2x4s out to the length of the proposed eaves and connect them with tape so the impact can be seen and then to take pictures from the houses that may realize a view impact.  (Mr. Moore subsequently submitted pictures from lots 7/13-16, 7/20, 7/23, 7/27, 7/28 and 7/34.  In addition, he submitted signed statements of non-objection from Moglia (7/13) and Sackman (7/14).  The Committee concluded there will not be any material view impact and approved the addition of eaves to the north and east sides of the garage.)

 

SACKMAN 7/14 (44280 O’Rorey’s Roost):  7/14/08  Receipt of update on construction status.  The Sackmans are trying to get a completion date from their contractor and will need a permit extension. 

 

UNFINISHED BUSINESS

 

FREIS 1/015 (15120 Irish Beach Dr.):  Receipt of a letter from William Moores stating that an non-permitted storage shed has been constructed.  The Committee sent letter of inquiry to the Fries on 5/30/08.  The Fries responded on 6/11/08 stating that the garbage and propane tank enclosure was rebuilt in the same location after being damaged last December. 

 

survivor trust 1/059 (14800 S. Hwy 1):  The IBADC wrote a second letter to Cal Fire on 3/31/08 requesting them to inspect the abandon property for fire hazards and to take appropriate action.  Cal Fire responded on 4/4/08 stating that a Defensible Space inspection was done and the results sent to the property owner.  Follow-up inspections will also be done. 

 

GMEINER 7/23 (44370 O’Rorey’s Roost):  4/7/08  Receipt of a letter regarding construction delays for permit 0702-0723.  Mr. Gmeiner has not yet detailed the delays he may have encountered during construction.

 

OWNER/BUILDERS:  The IBADC has asked several owner/builders in Irish Beach to comment on how to handle owner/builders who intend to take much longer to complete exterior construction than presently handled by the CC&Rs and procedures.  (See minutes of 3/17/07 and 5/19/07.) 

 

 

ADJOURNMENT/NEXT MEETING

 